Improving access through Ravenscraig

Next steps and timeline

The project will be delivered as part of the Glasgow City Region City Deal.

This is a large and complex project that will take several years to complete and will be delivered in different phases. This will ensure the new infrastructure is delivered when it's needed, while also ensuring investment in the development of the masterplan is maintained and our financial commitment is managed alongside its many priorities. 

The first thing we have done is create a new railway bridge that the road will go under and connect with Ravenscraig.

The dates we expect the different works to start

Ravenscraig Access Infrastructure South

  • Completing the bridge crossing under the West Coast Main Line Railway - completed September 2023.
  • Building the dual carriageway from Ravenscraig Regional Sports Facility to Motherwell and the junction at Airbles Road/Windmillhill Street:
  1. Site clearance and building demolition works begin summer 2024.
  2. Advance groundworks to end autumn 2025.
  3. Main work to begin at the end of 2025 and be completed during spring 2027.
  • Completing the dualling of Airbles Road to begin early 2028 and finish spring 2029.  

Ravenscraig Access Infrastructure North

  • Upgrading 3km of the A723 from the New Craig Road junction at Ravenscraig to the M8 at Holytown - the construction programme to be updated during 2024.

Page last updated:
14 Jun 2024

Help us improve this pageClose

We're sorry this page didn't meet your expectations this time. Please let us know if you have any feedback to help us improve the content.

If you have a question or comment about a council service or would like a reply, please contact us.

Thank you for your feedback