Investment programmes

Overview

The overview provides a summary of the four major investment programmes for schools and facilities that have taken place in North Lanarkshire since 2005.

More detail on each programme is provided in the related pages and a comprehensive listing of all projects and costs (where relevant) is available to download - 

ACTIVE Programmes

2015 - 2019 Schools and Centres 21 -Design and Build Framework Phase 2

The Phase 2 framework has been procured on the basis of a value of up to £200million to provide flexibility over four years however the council's internal cap for procuring projects via the framework is currently £100 million. The procurement concluded in November 2014 and three framework appointments were entered into in January 2015.

Current Value: approx £100 million capital

Current Projects: 4 

2013 - *Schools and Centres 21 - Hub Schools

Hub South West Scotland are delivering new build facilities on behalf of the council for three education establishments across two project sites in North Lanarkshire as well as undertaking some strategic services on one further campus project.*The Greenfaulds high school project has a service period of 25 years.

Current Value: approx £60 million capital

Current Projects: 3

The full list of these two active programmes are listed in this download pdf icon Schools and Centres 21- Active Projects [80kb] The following link provides a snapshot of the current progress pdf icon SC21 Active Programmes -Snapshot [202kb]

COMPLETED Programmes

2008 - 2013 Schools and Centres 21 - Design and Build Framework Phase 1

North Lanarkshire Council procured its first Schools and Centres 21 design and build capital funded £200million framework in 2008 and entered into four-year framework agreements with three partners. The framework delivered a mix of new build and modernised facilities for 14 education and five community establishments across 10 project sites in North Lanarkshire.

Capital Value: approx £196 million

Total Projects: 10

2005 - 2008 * Education 2010 Public Private Partnership

This major investment programme delivered all new build facilities for 24 school establishments and five community facilities across 17 project sites in North Lanarkshire through a revenue funded public private partnership procurement.  *The design, build, finance and maintain project agreement has a service period of around 30 years.

Capital Value: approx £154 million

Total Projects: 17

The full list of completed projects can be found here pdf icon Completed programmes [70kb]

To view progress images on all current projects please see our Progress diary page.

Please use the 'contact us' box if you have any questions. For more information, see 'downloads'.